Work activity
• 100-200 blocks: Crews continue work on subgrade in anticipation of future paving.
• Lewis Street: The team has completed the utility work at the Lewis Street
intersection. Crews will begin concrete pouring in the intersection.
• 3rd Street intersection (north side): Work will begin Tuesday, closing off vehicle and pedestrian access to the north side of the 3rd Street intersection. Pedestrians may access the north side of main street from 4th and Hot Springs crosswalk during the work period. Anticipate the closure to last three weeks.
• 400 block (south side): Crews will begin pouring curb and gutter followed by sidewalks.
• Pedestrian safety: Pedestrian crosswalks are open at 4th, 5th, 7th and 8th streets as an alternative to access businesses along Lewis Street or anywhere on the 400 block. Our team continues to see pedestrians not practicing good safety measures, jumping barricades and crossing U.S. 160. Our work zone is extremely active in several locations, and we want to keep everyone safe.
Stay informed and connect with the project
• Call the project information line: (970) 335-9230.
• Email the project team: Pagosa160reconstruction@gmail.com.
• Visit the project website: www.codot.gov/projects/us160pagosasprings.
• Subscribe to project updates: subscription.cotrip.org.