U.S. 160 reconstruction information

Posted

Week of June 22-28

Work activity

• Hot Springs Boulevard intersection: Paving operations are anticipated to be completed by the end of the day on Thursday, June 18. This will allow the team to reopen Hot Springs Boulevard to traffic as well as open the overlook parking lot. Pedestrian detours remain in place in several locations throughout the project limits.

• Fourth of July holiday: Crews will not be working July 3-6 in recognition of the holiday. The WW Clyde team will have a supervisor and traffic control specialist on call over the weekend should any needs come up around the work zone.

• Lewis Street: The intersection closure at Lewis Street and U.S. 160 remains in place. Please utilize 4th, 7th and 8th streets as an alternative to access businesses along Lewis Street. The good news is that the complex utility line work is mostly complete at this intersection. Crews have completed water utility work, wastewater utility work and electrical work. Some geothermal and stormwater utility work remains at this intersection, and is slated for the coming week, followed by concrete paving and sidewalk.

Stay informed and connect with the project

• Call the project information line: (970) 335-9230. 

• Email the project team: Pagosa160reconstruction@gmail.com.

• Visit the project website: www.codot.gov/projects/us160pagosasprings.

• Subscribe to project updates: subscription.cotrip.org.