U.S. 160 Wolf Creek Pass and Colo. 151 to fully open through winter

More permanent highway reconstruction scheduled for spring 2027

Posted

Two critical highways connecting southwestern Colorado to the rest of the region are scheduled to fully open ahead of winter and in time for holiday travel.

U.S. 160 Wolf Creek Pass will officially open to through travel on Saturday morning, Nov. 21,  at 7 a.m.

Colo. 151 is anticipated to open early next week, before Thanksgiving. After the devastating flood damage, reopening these routes will cut down on lengthy detour times and help the region regain a much-needed sense of normalcy. 

"Our top priority was getting these critical repairs done safely before winter conditions made construction impossible," said CDOT Executive Director Shoshana Lew. “This reopening reconnects southwest Colorado communities impacted by the historic flood events to the rest of the state. Essential transportation services and visitors have regained direct access to communities like Pagosa Springs, who depend on tourism year-round.”  

While both highways are safe for travel, crews will continue to perform additional road repairs in the coming weeks as weather conditions allow. CDOT urges motorists to remain alert, obey posted speed limits, and prepare for changing traffic patterns or lane shifts. Additionally, single-lane alternating traffic with full stops will remain in place at a few locations until full reconstruction can be performed this coming spring. Travelers should allow for extra travel time due to these stops and delays.  

“Although the highways have reopened, long-term permanent repairs and reconstruction will be needed in the coming years.” said Julie Constan Regional Transportation Director. “Our construction teams made strong progress completing critical temporary repairs ahead of winter weather settling in, now the focus is on long range projects that improve roadway resiliency for future flood events.” 

Opening Colo. 151 will eliminate a lengthy 3.5-hour detour through New Mexico for motorists traveling between Pagosa Springs and Durango. U.S. 160 remains closed due to the collapsed Piedra Bridge (MP 121). The southerly bypass along Colo. 151 and Colo. 172 via Ignacio, takes approximately 1 hour and 45 mins.

U.S. 160 South Fork to Pagosa Springs: Opens Saturday, 7 a.m.

U.S. 160 Wolf Creek Pass (MP 151 to 184) is scheduled to fully open on Saturday, Nov. 21, at 7 a.m. and is expected to remain open for the foreseeable future with the following travel impacts:  

  • Plan ahead and allow at least 60 minutes of additional travel time between Pagosa Springs and South Fork as road repair work will be ongoing at multiple locations 

  • Motorists will encounter up to 20 minute delays and 24/7 single-lane alternating traffic guided by temporary signals at three separate locations between South Fork and the Pagosa Springs (MP 151, 175 and 176)

  • Motorists are urged to slow down and be alert while navigating shifting traffic patterns and narrow or reduced lanes with concrete barriers in place between Treasure Falls and the Wolf Creek summit (MP 160 to 162)

Colo. 151 Pagosa Springs to Ignacio/Durango - Opens before Thanksgiving
Colo. 151, south of Chimney Rock (MP 27 to 30) anticipated to fully open early next week ahead of Thanksgiving and is expected to remain open with the following travel impacts:

  • A speed reduction of 45 mph will be enforced between MP 27 to 30, motorists are urged to slow down now along the rural bypass, including Colo. 151 and Colo. 172.

  • Stay alert and watch closely for vehicles entering and exiting the highway at driveways.

  • Livestock and wildlife are active along this corridor especially at dawn, dusk and nighttime — maintaining slower speeds is essential. 

  • Road repair will be ongoing at multiple locations between Ignacio and Chimney Rock as weather conditions allow.

U.S. 160 Durango to Pagosa Springs - Closed through mid-December  
U.S. 160 between Pagosa Springs and Durango at the Piedra River Bridge (Mile Point 121) remains closed to travel. CDOT is prioritizing a phased restoration process to open this critical route to motorists as soon as possible. A temporary road is being constructed and anticipated to be open to one-lane alternating traffic by mid-December. A temporary bridge supporting two-way traffic will be placed ahead of spring runoff, with permanent bridge construction anticipated to be complete by early 2028.