On Tuesday, Nov. 17, Colorado Department of Transportation (CDOT) representatives provided updates on highways around the county and the U.S. 160 reconstruction project winter shutdown to the Archuleta County Board of County Commissioners (BoCC) and Pagosa Springs Town Council at their respective meetings.
U.S. 160 reconstruction
The U.S. 160 downtown reconstruction project’s public information manager, Meredith Greene, explained, “We are going to be going into winter shutdown on the U.S 160 reconstruction project prior to Thanksgiving.”
She noted the shutdown is for “a variety of reasons,” but indicated that crews have been working on “buttoning up” areas of the project over the past week with asphalt paving at Harman Park, and the intersections with 8th Street and 1st Street.
Greene explained that the section from 1st Street through 5th Street is in its final configuration, with striping planned in the upcoming week.
She noted that people will be able to park in front of businesses, but that final parking striping will not occur until 2027.
Greene also mentioned that CDOT is looking to change the wide-load restriction through downtown due to the amount of heavy equipment coming through the area for flood response and recovery.
Greene also noted that crews will finish paving driveways on the south side of U.S. 160 from 5th Street to 8th Street, but explained that 6th Street and 7th Street will remain closed through the winter.
“People will have access via 8th Street,” she said.
Greene explained that the Town of Pagosa Springs opted to leave 6th Street closed due to damage the roadway sustained from the floods.
She also added that CDOT and the town are working in collaboration on a snow removal plan for U.S. 160, and that a “frequently asked questions” list for the project is being developed.
“We will be providing quite a bit of information,” Greene said.
She emphasized that while crews are going into winter closure, “we’re not going away.”
She explained that there will still be people on-site to monitor the project throughout the winter season.
Greene explained that once crews return in spring 2027, they will have 80 working days left on the project, or about two and half months.
She also noted that there is not much utility work left, other than some electric street lighting, “as well as some potential geothermal work” near the “dogleg” section.
In response to a question from Commissioner John Ranson, Greene commented that crews will be “very purposeful about our return” in the spring and work to finish the project as quickly as possible.
Greene added that with the extra demand on materials and the availability of resources, “and the fact that our team is being retooled to focus on emergency recovery and emergency repair efforts, we felt that this was the best time to go into the winter shutdown.”
In addition to hearing about the project’s winter shutdown and plans, the town council also hear from CDOT representative Tracey Trulove about the fencing that has been placed in the median of the 400 block of main street.
“Our team got a few questions about the current fencing that’s in the median, and I think that y’all might want to be aware that that’s a conversation that’s been happening in our channels,” Trulove said, adding, “The Town of Pagosa and the CDOT team are staying in conversation about what the snow removal will look like.”
Mayor Shari Pierce asked Development Director James Dickhoff if he could address how snow removal will be handled with the fence in the median.
“We originally contemplated this fence during a flyover for the main street project,” Dickhoff said, adding, “The landscaping did not go in yet this year. We just couldn’t pull it off. We had planned to do that right before the floods.”
He also mentioned that “the purpose of the fence was really to discourage jaywalking in this section of the 400 block, which was pretty prevalent previously. So, that was the purpose of the fence that we contemplated about a year ago or so.”
Dickhoff also indicated that he has met with the new regional maintenance supervisor for CDOT, “and he has it on his calendar to meet with us” regarding snow removal.
“In general, I think the plan is to push the snow to the center, where there’s not a median, and then the town would come by, like we have in the past, and scoop the snow and move it out to a remote location,” Dickhoff said.
Council member Gary Williams commented, “Clearly the aesthetic of this fence is not very good … and what’s the process moving forward to use landscaping to discourage jaywalking instead of the fence? And do we need CDOT’s permission to remove the fence, I guess is what I’m asking.”
Dickhoff responded that “it is the town’s fence,” explaining, “We are obligated to maintain that median. It’s not CDOT’s responsibility … and we have not seen any success in landscaping in preventing people from walking through those areas.”
Williams suggested “yucca and cactus,” with council member Madeline Bergon saying, “I would also suggest thorny bushes.”
Piedra River bridge
CDOT Region 5 Transportation Director Julie Constan explained to the BoCC that within days after losing the Piedra River bridge following the flood on Nov. 1 and 2, CDOT brought in engineers and contractors, and “quickly began assessing what we can do out there.”
She noted that multiple options were considered, and “where we landed” involves bringing in six 72-inch diameter culverts to be placed in the river and having a one-lane paved highway on top.
Constan commented that CDOT is “cautiously optimistic” to have the culverts and one-lane temporary highway paved by the first week of December.
“This will allow us to have some kind of traffic through there,” she said, explaining that it will be a temporary solution until late February or early March 2027.
She went on to explain that a temporary Acrow bridge will then be installed, allowing two-way traffic, and that CDOT will be designing a permanent solution by the end of 2027 or into 2028.
Commissioner Warren Brown commented on CDOT’s response to the roadway destruction, saying, “I appreciate CDOT’s ability to pivot during this difficult time and get us as much access and connectivity as possible.”
Colo. 151
Constan explained that Colo. 151 had two washout locations over the course of the two flooding events: one at mile post 27 and one at mile post 30.
She explained that the work that crews were able to do after the first storm held up through the second storm, but unfortunately a new washout occurred.
Constan also noted that crews have been able to pave a new road at mile post 27, allowing residents in and out of the area with access from the south.
She mentioned that culverts have been ordered for mile post 30 and that the section will be paved “hopefully no later than Friday [Nov. 20] this week.”
She also explained that CDOT is looking at speed reductions through “due to the volume of traffic that’s gonna be on that highway,” noting that the usual U.S. 160 traffic will end up on Colo. 151.
Brown asked about the possibility of a temporary traffic light at the intersection with County Road 928, explaining that residents have been having trouble “getting out on that semi-blind corner.”
“We’ll take a look at that,” Constan replied.
Commissioner Veronica Medina also inquired about damage occurring on county roads 973 and 975, noting that big trucks are speeding and “it’s become a hazard.”
Constan acknowledged the concern and indicated that she would reach out to crews.
Jackson Mountain
Constan explained that “pretty significant movement and sloughing” has occurred at mile post 151.3 on U.S. 160 in what is known as the Jackson Mountain slide area.
She mentioned that the section of highway has been “moving for years,” and that CDOT performed stabilization work in 2012 and 2013.
She explained that work “has held and did well,” but that a new area adjacent to it is now moving.
Constan mentioned that CDOT is monitoring the area and performing tests in order to understand how much at risk the highway is “because our whole goal is keep that highway open through the winter,” noting the permanent stabilization work will occur in spring 2027.
“So, that is why we do have it down to one lane,” she said, indicating that the alternating signals will likely be in place for a “decent part of winter.”
Wolf Creek Pass
Constan also mentioned that the east side of Wolf Creek Pass in the “narrows” sections is currently being paved as the goal is to have the pass opened by this Friday, Nov. 20.
She explained that on the west side of the pass, there are two sections with concrete barriers that will remain in place over the winter, due to part of the road “just hanging in thin air.”
She noted that crews are working on drainage ditches on the uphill side between the cliff and highway that “were dug very deep,” with 3- to 5-foot drop offs right next to the pavement.
“We’re getting that squared away,” she said.
Medina commented that the accessibility into Pagosa Springs has been “top of mind,” adding that she was happy to hear the progress being made, noting this is “very important information for our community.”