U.S. 160 reconstruction team offers answers to frequently asked questions

Posted

As the 2026 construction season comes to a close, the Colorado Department of Transportation (CDOT) and WW Clyde are transitioning the U.S. 160 reconstruction project into winter shutdown.

While major construction activities will pause during the colder months, the project team will maintain a presence in Pagosa Springs, monitor conditions throughout the project area and prepare for the final phase of construction in spring 2027.

Winter shutdown and project schedule

• When does the project officially enter winter shutdown?

The project entered winter shutdown the week of Nov. 23. Major construction activities will pause until spring, when weather and ground conditions are more favorable for completing the remaining work.

• Why is construction shutting down for the winter?

Winter weather, freezing temperatures, snowfall and ground conditions limit the types of construction activities that can be performed safely and effectively.

Pausing major construction operations during the winter helps protect the quality and integrity of the improvements being made while supporting safe travel through the project area.

• When will construction resume?

The project team anticipates resuming construction in March or April 2027, depending on snowfall, temperatures, ground conditions and other weather-related factors. A more specific restart date will be communicated to the community as spring approaches.

• Is the project expected to be completed in 2027?

Yes. The upcoming construction season is anticipated to be the final phase of the U.S. 160 reconstruction project. The team will return in spring 2027 to complete the remaining construction activities and associated finishing work. Additional details regarding the completion will be shared prior to spring construction.

Remaining construction activities

• What work remains to be completed in spring 2027?

While significant progress has been made over the past two construction seasons, several areas require additional work.

Remaining construction activities include improvements along the south side of US 160 and at the following intersections: 5th Street, 6th Street, 7th Street, 8th Street, 10th Street and the Harman Park/Piedra Road area.

The project team will provide more detailed information regarding traffic impacts of these activities before construction resumes.

• Will all remaining construction areas be worked on at the same time?

The project team will evaluate the sequencing of remaining construction activities to balance construction efficiency, safety, traffic mobility, and access to local businesses and properties.

Winter maintenance and snow removal

• Will construction crews remain in Pagosa Springs during the winter shutdown?

Although major construction activities will pause, the project team will maintain an on-site presence throughout the winter to monitor the project area, assess conditions and address construction-related concerns as necessary.

Residents and businesses may occasionally see project personnel or equipment within the corridor during the winter months. This is part of ongoing project monitoring and maintenance and does not necessarily indicate that full construction operations have resumed.

• How will snow removal be handled throughout the construction area?

The project team is working closely with CDOT and the Town of Pagosa Springs to coordinate a winter snow removal plan that accounts for the current roadway configuration, completed improvements and remaining construction areas.

The goal is to support safe travel, maintain access and protect newly installed infrastructure. Snow removal procedures may be adjusted throughout the winter in response to weather events and changing conditions.

• Who should I contact if I have a snow removal or construction-related concern?

Residents and businesses with concerns related to snow removal within the construction area, temporary traffic control or other construction-related conditions are encouraged to contact the project hotline or email.

The project team will coordinate with the appropriate agency or personnel to address concerns as needed.

• Will the project area continue to be monitored during significant winter weather events?

The project team will continue monitoring conditions throughout the winter shutdown. Coordination among the project team, CDOT and the town will remain important as snowfall, freezing temperatures and snowmelt affect the corridor.

Traffic, parking and
business access

• Will traffic patterns change during the winter shutdown?

The project team anticipates maintaining the established winter traffic configuration until construction resumes. However, temporary adjustments may be necessary due to weather conditions, maintenance activities or safety concerns.

Motorists should continue to follow posted signage, pavement markings and temporary traffic control devices.

• Why are some construction signs, cones, and barricades still in place?

Although major construction activities have paused, portions of the project remain unfinished. Temporary traffic control devices are necessary in certain locations to protect motorists, pedestrians and infrastructure until construction can be completed.

Please do not move or remove construction signs, cones or barricades, even when crews are not actively working.

• Will South 7th Street remain closed throughout the winter?

Yes. Due to construction delays associated with significant rainfall and flooding, South 7th Street will remain closed at U.S. 160 throughout the winter shutdown. Access to the area will continue to be available via South 8th Street.

The project team anticipates completing the remaining work and reopening the intersection in spring 2027, weather and construction conditions permitting.

• Are downtown businesses accessible during the winter shutdown?

Yes. The project team encourages residents and visitors to continue supporting downtown Pagosa Springs businesses throughout the winter. Please follow designated pedestrian routes, posted parking restrictions and any temporary access signage.

We appreciate the continued resilience and cooperation of our local business community throughout the reconstruction project.

• What should motorists and pedestrians keep in mind when traveling through the project area this winter?

Although active construction has paused, the corridor remains a construction zone with some temporary conditions in place. Motorists and pedestrians are encouraged to:

Follow all posted speed limits, signage, and traffic control devices.

Adjust driving speeds to winter weather and roadway conditions.

Park only in designated or legally permitted areas.

Use designated pedestrian routes and crossings.

Remain alert for snow removal equipment and project personnel.

Staying informed and connected

• Will the project hotline and email remain active during the winter shutdown?

Yes. The project hotline and email will continue to be monitored throughout the winter shutdown. Residents, businesses and community members are encouraged to contact the project team with construction-related questions or concerns.

• Will the community continue to receive project updates during the winter?

The project team will continue to provide updates as needed throughout the winter, particularly if there are significant changes to traffic conditions, access or the anticipated spring construction schedule. As construction resumes in 2027, the team will provide additional information regarding upcoming activities, anticipated closures, traffic shifts and construction milestones.

• How can I stay informed or contact the project team?

Project hotline: (970) 335-9230

Project email: Pagosa160reconstruction@gmail.com

Project webpage: www.codot.gov/projects/us160pagosasprings.

For emergencies, please call 911.

A thank you to our
community

CDOT and WW Clyde sincerely appreciate the patience, cooperation and support of the Pagosa Springs community throughout the past two construction seasons.

Although construction is temporarily pausing, our commitment to the community and the successful completion of this important project remains unchanged.

We look forward to returning in spring 2027 to complete the remaining improvements and continue building a better main street together.

From your U.S. 160 reconstruction project team, we wish everyone a safe and happy winter season.