Over the last week, U.S. 160 over Wolf Creek Pass and Colo. 151 have reopened to traffic, with the Colorado Department of Transportation (CDOT) making clear work on the stretches of highway is continuing, as well as on U.S. 160 over the Piedra River.
The agency has also made it clear the work was done with the help of Emergency Relief quick-release funds from the Federal Highway Administration (FHWA) after CDOT estimated $156 million in flood damage to the region’s highways.
Wolf Creek Pass
U.S. 160 over Wolf Creek Pass reopened on Saturday, Nov. 21, though CDOT warns travelers via a Nov. 22 press release to plan ahead and allow at least 60 minutes of additional travel time between Pagosa Springs and South Fork due to ongoing road repair work.
CDOT explains motorists will encounter up to 20 minute delays and 24/7 single-lane alternating traffic guided by temporary signals at three separate locations (mile posts 151, 175 and 176).
Motorists are urged to slow down and be alert while navigating shifting traffic patterns and narrow or reduced lanes with concrete barriers in place between Treasure Falls and the Wolf Creek summit (mile posts 160 to 162).
Colo. 151
Colo. 151 reopened to travel the evening of Monday, Nov. 23, with CDOT explaining on Nov. 22 crews had been working 24/7 for the past 20 days to reconstruct the highway.
CDOT advises that the entire stretch of Colo. 151 from Ignacio to the rebuilt stretch of highway (mile points 0 to 31) is considered a managed construction zone.
Ongoing maintenance is taking place at several locations along the entire stretch of highway, CDOT explains. Temporary speed reductions will be in effect at all active work zone sites. Motorists must abide by 25 mph speed limits where flaggers are present, or 45 mph where a physical barrier is present. Motorists are urged to be alert to decreases in speed limits as they approach work zones and allow for extra travel time.
“We urge travelers to be attentive and extremely cautious, particularly on Highway 151,” said Regional Transportation Director Julie Constan via the press release. “This is a two-lane, rural highway that meanders through several small communities, farms and ranches. The road is curvy and hilly in areas with limited sight distance and hidden driveways. Please take it slow.”
CDOT also warns that livestock and wildlife are active along this corridor, especially at dawn, dusk and nighttime, and maintaining slower speeds is essential.
U.S. 160 at Piedra River
U.S. 160 at the Piedra River bridge remains closed between Durango and Pagosa, with plans to have a one -lane configuration prior to Christmas, according to CDOT.
CDOT notes the southerly bypass along Colo. 151 and Colo. 172 via Ignacio takes approximately 1 hour and 45 minutes between Pagosa Springs to Durango.
“CDOT is prioritizing a phased restoration process to open this critical route to motorists as soon as possible,” the press release notes. “A temporary road is being constructed and will first be open to one-lane alternating traffic once completed. A temporary bridge supporting two-way traffic will be placed ahead of spring runoff, with permanent bridge construction anticipated to be complete by early 2028.”
CDOT further notes that travel times along these routes could be impacted by ongoing construction work or winter weather conditions.
Motorists are reminded to visit COtrip.org or utilize the COtrip Planner App for the most current construction impacts and road conditions.
Additional $9.1 million in quick release funds approved
On Monday, Nov. 23, the state and CDOT announced the FHWA has approved $9.1 million in additional quick-release Emergency Relief funds to help repair highways and eligible local roads damaged by back-to-back storms in Southwest Colorado.
The funding comes as CDOT updated its estimate of flood damage to $156 million, up from an initial estimate of $65 million after the first storm. The second estimate accounts for the second consecutive weekend of flooding that impacted southwest Colorado.
Funding through the FHWA is separate from funding requested through the governor’s second presidential major disaster declaration request that was submitted to the Federal Emergency Management Agency last on Friday, Nov. 20.
For more on that request, see related article.
The $9.1 million is in addition to the $6.5 million FHWA approved earlier this fall due to damage from the year’s first flood, bringing the total quick release funding to $15.6 million.
The state notes that $15.6 million includes $600,000 for county roads, which is 10 percent of an estimated $6 million in damage to local roads.
CDOT requested the funds on behalf of the counties and will be working with counties to identify damages that will be eligible for this federal program as damage assessments continue to be conducted, it notes.
“I am thankful for these additional emergency funds from the Federal Highway Administration. Getting this funding now means that construction crews can do more emergency repairs ahead of winter. Southwest Colorado has been impacted by multiple devastating floods, and fixing roads and highways is an important part of getting back on our feet,” said Gov. Jared Polis.
“Southwest Colorado has been dealing with major impacts, not only with their roads but their everyday lives, and we’re grateful to the Federal Highway Administration for moving so quickly on this second round of immediate funding,” said CDOT Executive Director Shoshana Lew. “These dollars let our crews and contractors keep working on emergency repairs without delay, and have already been critical in achieving key milestones like getting Wolf Creek Pass and Colo. 151 open before Thanksgiving. We truly appreciate the quick attention from FHWA and the continued support from Sen. [Michael] Bennet, Sen. [John] Hickenlooper and Congressman [Jeff] Hurd.”
The $156 million figure is an estimate, and CDOT staff expressed that it expects the figure to change as inspections and assessments continue.
The $156 million total request to the federal government will be augmented by $20 million in state emergency contingency funds authorized by the Colorado Transportation Commission. CDOT has stated it will request additional federal Emergency Relief funding as damage is verified.
randi@pagosasun.com