U.S. 160 reconstruction information

Posted

Week of Aug. 17-22

Work activity

• Overlook parking lot: Sidewalk work continues along U.S. 160 next to the overlook parking lot. Parking spaces will be closed in areas where work is taking place.

• North 7th Street: Crews are initiating storm water drain replacement and utility work. Pedestrians should use the alternative street crossing at 8th Street.

• South 7th Street: Work continues on water utility connection work with PAWSD followed by safety improvements. Residents should plan on 7th Street being closed for a month.

• North 3rd Street intersection: Work continues on the subgrade as crews prepare for paving operations. Pedestrians may access the north side of main street from the 4th Street and Hot Springs Boulevard crosswalk during the work period. This intersection is expected to open late August, pending weather delays.

• 100 and 200 blocks: Crews will continue paving the south side of U.S. 160 from 3rd Street to the east.

• Pedestrian safety: Pedestrian crosswalks are open at 4th, 7th and 8th streets as an alternative to access businesses along Lewis Street or anywhere on the 400 block. Our team continues to see pedestrians not practicing good safety measures, jumping barricades and crossing U.S. 160. Our work zone is extremely active in several locations, and we want to keep everyone safe.

Stay informed and connect with the project

• Call the project information line: (970) 335-9230.

• Email the project team: Pagosa160reconstruction@gmail.com.

• Visit the project website: www.codot.gov/projects/us160pagosasprings.

• Subscribe to project updates: subscription.cotrip.org.