U.S. 160 reconstruction information

Posted

Week of Aug. 24-30

Work activity

• The 7th Street intersection closure will continue through mid-September as crews work to complete utility and safety upgrades. Please note that pedestrians and vehicles should utilize 5th and Lewis and 8th Streets as alternatives to cross U.S. 160.

• Overlook parking lot: Sidewalk work continues along U.S. 160 next to the overlook parking lot. Parking spaces will be closed in areas where work is taking place. 

• North 3rd Street intersection: Crews have completed concrete paving work, and will reopen North 3rd Street as they prepare for asphalt paving operations to connect the new pour with the older sections of 3rd Street. Asphalt paving work will take place the week of Aug. 31.

• Work is scheduled to commence at the Harman Park and Piedra Road intersection at U.S. 160 in mid-September. Please allow extra time to get through the work zone.

• Pedestrian safety: Our team continues to see pedestrians not practicing good safety measures, jumping barricades and crossing U.S. 160. Our work zone is extremely active in several locations, and we want to keep everyone safe.

Stay informed and connect with the project

• Call the project information line: (970) 335-9230. 

• Email the project team: Pagosa160reconstruction@gmail.com.

• Visit the project website: www.codot.gov/projects/us160pagosasprings.

• Subscribe to project updates: subscription.cotrip.org.